Minggu, 18 Desember 2011

ANGGARAN BIAYA


ANGGARAN BIAYA

Nama Proyek       : Pembangunan Komplek Pesantren Pasambangan Jati
Alamat Proyek     : Blok Simuprit RT 02 RW 02
                              Desa Penpen Kecamatan Mundu Kabupaten Cirebon

No.
Jenis Barang dan Tenaga
Satuan
Harga Satuan
Jumlah (Rp)

(@Rp)

1
Batu Kali
150
rit
  210,000
31,500,000

2
Batu Merah
180000
biji
 400
      72,000,000

3
Besi 10 inch
2000
bt
 45,000
90,000,000

4
Besi 12 inch
800
bt
 49,000
39,200,000

5
Besi 8 inch
3000
bt
    28,000
84,000,000

6
Besi 6 inch
900
bt
    16,000
14,000,000

7
Besi 16 inch
120
bt
      76,000
9,000,000

8
Besi Pagar
115
m
        700,000
80,500,000

9
Pasir Pasang
3000
rit
       180,000
540,000,000

10
Pasir Urug
147
rit
        160,000
23,000,000

11
Seplit (batu beton)
340
rit
     500,000
170,000,000

12
Kayu Kusen Kamper
50
kubik
  4,500,000
225,000,000

13
Kayu Kap
40
kubik
 2,500,000
100,000,000

14
Kayu Reng
400
ikat
 200,000
80,000,000

15
Kayu Kaso 5 x 7 cm
750
ikat
120,000
28.800.000

16
Kayu Kaso 4 x 6 cm
288
ikat
80,000
23.040.000

17
Papan Risplang
48
bt
  80,000
90,000,000

18
Papan Cor
2500
batang
 25,000
62,500,000

19
Semen
5000
sak
  50,000
250,000,000

20
Kawat Tali
400
kg
  15,000
6,000,000

21
Paku
1500
kg
 16,000
24,000,000

22
Keramik
1500
m2
48,000
72,000,000

23
Daun Jendela
340
stel
       450,000
153,000,000

24
Daun Pintu
90
stel
   2,000,000
180,000,000

25
Plamur Tembok
50
kaleng
     210,000
10,500,000

26
Menie Kayu
20
kaleng
  25,000
500,000

27
Cat Tembok 25 kg
65
kaleng
 370,000
24,050,000

28
Cat Kayu ukuran 1 kg
145
kaleng
    60,000
8,700,000

29
Plamir Kayu (Impra)
35
Kaleng 
 50,000
1,750,000

30
Karpus
980
biji
5,000
4,900,000

31
Genteng Munir
32600
buah
3,000
97,800,000

32
Triplek
500
lembar
120,000
60,000,000

33
Paralon 2 in
300
batang
 45,000
13,500,000

34
Bilboard 2 x 4 m
60
buah
350,00
21,000,000

35
Paving Blok
300
m
     35,000
10,000,000

36
Tenaga Tukang 15org
1080
hari
45,000
729,000,000

37
Tenaga Kernet 45org
1080
hari
  35,000
1,701,000,000

JUMLAH TOTAL
5,130,000,000








REKAPITULASI ANGGARAN BIAYA :




1.
Jumlah Material



2,700,240,000

2.
Jumlah Tenaga Kerja



2,430,000,000

Jumlah Total

5,130,000,000


Terbilang : Lima Milyard Seratus Tiga Puluh Juta Rupiah.

Tidak ada komentar: